Gearing
up for the implementation of the Air Quality Act
- Department of Environmental Affairs and Tourism
- MONDAY, 16 October 2006:
MINISTRY OF ENVIRONMENTAL AFFAIRS
AND TOURISM
REVISED RECORD OF DECISION: DE HOOP DAM
RECORD OF DECISION
RECORD OF DECISION FOR PROJECT
REFERENCE 12/12/20/553 OLIFANTS RIVER WATER RESOURCES
DEVELOPMENT PROJECT (PHASE 2): INFRASTRUCTURE
DEVELOPMENT
By virtue of the power granted
to me in terms of section 33(1) of the Environment
Conservation Act, (Act 73 of 1989) (“the Act”),
I hereby, in terms of section 22(3) of the Act,
authorise the Department of Water Affairs and
Forestry to undertake the activity specified/
detailed below, subject to the indicated conditions.
1. DESCRIPTION, EXTENT AND LOCATION OF
THE ACTIVITY:
The construction of a large
storage dam (and associated spillway structure
and pump station) on the Steelpoort River at the
Farm De Hoop (with centre co-ordinates of 24o
57’ 30 ‘’ S; 29o 57’ 25 ‘’ E), approximately 27
km north of Roossenekal and approximately 40 km
south of Steelpoort. The dam will have a full
supply level of 915 masl, a wall length approximately
1 050 m and will inundate an area of about 1 690
ha.
A change in land use from agricultural use to
that of a Government Water Works as defined in
the National Water Act (Act 36 of 1998) through
the inundation of the basin (an area of about
1 690 ha).
The removal and/or flooding of existing vegetation
from the proposed dam inundation basin (an area
of about 1 690 ha).
The realignment of a section of the Provincial
Road between Roossenekal and Steelpoort (Road
P169) for a distance of approximately 25 km. This
realignment will be to the west of the proposed
dam immediately adjacent to the dam purchase line.
The road realignment will include three major
bridges, two across the Steelpoort River at either
end of the proposed dam and one across the Maseketi
River.
The construction of a bulk water pipeline from
the proposed De Hoop Dam or from the Steelpoort
Abstraction Weir past Atok Mine to Olifantspoort
Weir (primarily following the R34 and R37 roads).
This pipeline is inclusive of 3 pump stations,
off-takes, 3 balancing dams and one reservoir.
The construction of three gauging weirs ( (a)
at 25o 04’ S; 29o 50’ E, approximately 2 m above
river bed level and 30 – 50 m wide (b) at 24o
57’ S; 29o 57’ E, approximately 2 m above river
bed level and 30 – 50 m wide (c) at 24o 29’ S;
30o 24’ E, approximately 2 m above river bed level
and 60 – 80 m wide), and one abstraction weir
(at Steelpoort, approximately 5 m above river
bed level and 30 – 50 m wide) on the Steelpoort
river and off-channel desilting works associated
with the abstraction weir. All weir structures
will have associated access roads that will be
constructed.
The construction of the bulk water pipeline from
the proposed De Hoop Dam to Jane Furse, primarily
along the P169 and D2219. This pipeline is inclusive
of 3 pump stations, off-takes, 3 balancing dams
and 3 reservoirs.
The construction of a bulk water pipeline from
the Flag Boshielo Dam to Mokopane along the D885
and P18. This pipeline is inclusive of 4 pump
stations, off-takes, 4 balancing dams and one
reservoir.
The clearing and making safe of sites for road,
dam and pipeline construction camps, which includes
services, access roads (three main ones) and bridges
(one main bridge), powerlines, washbays, workshops,
offices, stores, and so forth, and the storage
of materials and explosives.
The installation of communication networks infrastructure.
The construction and operation of small-scale
sewerage treatment plants for construction camps.
The construction and operation of small-scale
waste collection and disposal facilities for construction
camps and sites.
The construction of facilities for the bulk storage
and dispensing of fuel (e.g. diesel and petrol)
for construction vehicles at the proposed dam
and weir sites, along pipeline routes and for
the road construction camp.
The creation of stockpiles of construction materials
for the construction of a dam, roads, pipelines
and living quarters, including batching and mixing
plants.
The installation and operation of bitumen plants
for the constructions of roads.
The excavation of borrow areas (inclusive of rock
quarries and crusher plants for all project components)
from which construction materials will be sourced.
There will be two main borrow areas for the dam,
one entirely within the area of inundation, and
one that potentially will only be partially inundated.
The construction of water treatment / purification
work at Mooihoek, between Steelpoort and Atok
Mine.
The above infrastructure is
described in Appendix 1 that includes figure 1,
where the infrastructure is illustrated. Infrastructure
is also described in detail in the Environmental
Impact Report (October 2005).
2. KEY FACTORS INFORMING
THE DECISION:
In reaching my decision in respect
of this application, I have, inter alia, taken
the following information into consideration:
The final environmental impact
report dated October 2005.
Comments received from the following authorities:
South African Heritage Resources Agency (SAHRA);
Department of Health and Social Services, Mpumalanga
Province;
Department of Minerals and Energy, Limpopo Province;
Department of Economic Development, Environment
and Tourism, Limpopo Province;
Department of Agriculture and Land Administration,
Mpumalanga Province.
The specialist report as submitted by external
experts, Prof. MT Seaman, Director of the Centre
for Management of the Environment at the University
of the Free State and associate professor in Water
Environmental Management; and Mr. C Bruwer, a
registered environmental scientist with the consultancy
EnviroAfrica.
The submission by the Department of Water Affairs
and Forestry (DWAF) regarding the bilateral held
between them and SANParks and the recommendations
emanating therefrom;
The analysis of the Record of Decision conducted
by the Environmental Assessment Practitioners
(ACER Africa) dated 16 January 2006;
The concerns raised by the appellants with regard
to the cumulative impacts associated with, inter
alia, further development pressure and water demands
on the catchment area and the Kruger National
Park.
The notes of a meeting held between the DWAF and
the appellants in June 2006; and
The DEAT’s response to the grounds of appeal.
In reviewing this information, the DEAT made the
following findings:
The proposed development arose, inter alia, as
a result of the need to provide the previously
disadvantaged communities with decent potable
water and to stimulate economic development in
the Greater Sekhukhune Municipality, the Capricorn
Municipality and the Mogalakwena Municipality.
During the scoping exercise, seven key issues
were identified and investigated. These examined
aspects related to:
Impact on quantity and quality of river flows;
Aquatic and terrestrial ecology;
Long-term sustainability and water demand management;
Capacity of the receiving environment;
Minimising construction-related impacts;
Land acquisition and compensation;
Co-operative governance.
Anticipated impacts associated with each of the
seven key issues have been assessed, and mitigation
measures have been proposed.
Cumulative impacts have been
adequately assessed in so far as they relate to
the scope of this EIA.
Aspects related to co-basin states are adequately
covered in the environmental impact report and
are being handled on an ongoing basis by a dedicated
task team within the DWAF.
The mitigation measures proposed in the environmental
impact report are appropriate and practical for
implementation. Particular attention is drawn
to the following:
The investigation of the establishment of an off-site
mitigation area to mitigate the loss of biodiversity
in the dam basin and around the dam wall.
The planning and implementation of the water conservation
and demand management strategy for the Olifants
Water Management Area in parallel with the construction
of infrastructure (i.e. approximately 10 years).
Facilitation, by the Department of Water Affairs
and Forestry, of co-operative governance (between
and within spheres of Government), in particular,
to prepare the receiving environment for a project
of this magnitude, as well as taking cognisance
of future developments enabled by this project.
Facilitation, by the Department of Water Affairs
and Forestry, of co-operative governance (between
and within spheres of Government), in mitigation
measures that require a collaborative intervention
and effort by the State.
Having considered the above information, I have
concluded that:
The need for the proposed dam
has clearly been demonstrated and there is no
viable alternative to a supply-side solution for
the envisaged demands on the system;
The dam has positive impacts, both in terms of
socio-economic and ecological aspects;
The construction and operation of the dam will,
however, have definite and substantial detrimental
impacts on the environment;
The substantial impacts cannot therefore be avoided,
but measures must be put in place to mitigate
the potential impacts to acceptable levels;
The Record of Decision issued on 21 November 2005
does not adequately mitigate and manage the detrimental
impacts and the grounds of appeals related to
some of the conditions and certain substantive
issues were therefore upheld;
The conditions enclosed in this revised Record
of Decision are deemed adequate to mitigate the
identified impacts to acceptable levels; and
Taking the mitigation measures enforced through
this revised Record of Decision into consideration,
the principles of section 2 of NEMA can be substantially
upheld.
I have accordingly decided to grant DWAF authorisation
in terms of Regulations R.1182 and 1183 (as amended)
promulgated under sections 21, 22 and 26 of the
Environment Conservation Act (Act 73 of 1989),
subject to the conditions and provisions listed
below.
3. CONDITIONS
3.1 Description and extent of
the activity
The authorization applies in
respect of the project as defined in Section 1
and Appendix 1, and as illustrated in Figure 1.
The proposed infrastructure is also described
in detail in the environmental impact report (EIR
– October 2005).
3.2 Specific conditions
3.2.1 Environmental Performance
3.2.1.1 The DWAF must maintain
the ecological reserve requirements of the Steelpoort
River downstream of the dam.
3.2.1.2. All man-made structures
of consequence must be removed from the flood
area of the dam and no development must take place
within the 1:100 floodline, other than for purposes
of the Government Water Works.
3.2.1.3. All liquid effluent
must be disposed of in a manner approved by the
relevant municipalities.
3.2.1.4 All waste generated
during the construction must be removed and disposed
of at a waste disposal facility permitted in terms
of section 20 of the Environment Conservation
Act, 1989 (Act No. 73 of 1989).
3.2.1.5 Hazardous and flammable
substances must be stored and used in compliance
with applicable regulations and safety instructions.
3.2.1.6 The applicant must place
cordons, barriers and warning signs around excavations
in the village sites and wherever there is a hazard
to workers, the public and animals.
3.2.1.7The applicant must train
safety representatives, managers and workers in
workplace safety and enforce all applicable physical
safety standards and regulations. This requirement
is also applicable to subcontractors.
3.2.1.8 The applicant must maintain
the early warning systems and disaster plans for
severe floods and, in the very unlikely event
of dam wall failure.
3.2.1.9 The applicant must provide
high standard warnings and traffic calming measures
where construction activities interfere with traffic.
3.2.1.10 The applicant must
implement dust abatement measures, such as the
wetting of active construction areas and unpaved
roads and the vegetation of the permanent stockpiles.
3.2.1.11 The applicant must
take note that no temporary site camps will be
allowed outside the footprint of the development
area as the establishment of such structures might
trigger a listed activity as defined in the NEMA
Regulations, Government Notice 386 and 387 of
2006.
3.2.1.12 The applicant must
provide sanitation facilities within the construction
camps and along the pipelines in order that workers
do not pollute the surrounding environment.
3.2.1.13 The applicant must
establish and maintain a conservation area of
equal size and similar nature to the area of the
Sekhukhune Land Centre of Endemism, to be flooded
or otherwise transformed as result of the building
of the dam, as mitigation for the loss of this
land. This conservation area must be established
at the time that the dam becomes operational.
The process for identification and establishment
of this conservation area must be discussed with
and agreed to by the DEAT.
3.2.2 Environmental Monitoring
Committee (EMC)
3.2.2.1 This development is
authorised on condition that the Department of
Water Affairs and Forestry (DWAF) establishes
an EMC with clear Terms of Reference (ToR) as
described in clause 3.2.2.7. Such EMC must be
established before commencement of any construction
activities.
3.2.2.2 Amongst others, the
EMC shall in so far as it is reasonably practicable,
consist of the following members:
A chairperson as described in
3.2.2.3;
The developer’s (DWAF) representatives;
Representatives of the affected residents / rate
payers’ association;
Ward councillors;
Non-Governmental Organisations;
Community leaders;
Representatives of Farmers Associations;
An Environmental Control Officer (ECO) (once appointed
in terms of 3.2.4.1); and
An aquatic and terrestrial ecologist/s.
Membership of the EMC as indicated in categories
(c), (d), (e), (f) and (g) will obviously be dependent
on the willingness of these organisations to be
represented on the EMC. Membership for these categories
of members is voluntary and no remuneration will
be payable to members in these categories.
3.2.2.3 The EMC must appoint
an independent chairperson who has appropriate
people and project management skills. It is not
compulsory to select the chairperson from the
membership described in 3.2.2.2 (b) – (i) above.
An individual meeting the skills requirement from
inside or outside the membership may be selected.
3.2.2.4 All costs associated
with the EMC are to be borne by the applicant.
The ToR for the EMC must, in addition to the scope
of work as detailed in 3.2.2.7, clearly set out
roles and responsibilities related to logistical
arrangements, administration and financial arrangements
associated with the EMC and its membership. This
must include the remuneration of the chairperson
and the ecologist/s specified in 3.2.2.2. (a)
and (i) above.
3.2.2.5 The EMC must meet on
a bi-monthly basis from the inception of the project.
3.2.2.6 The EMC must report
to the Director General of the Department of Environmental
Affairs and Tourism on a bi-monthly basis and
the report must include, at the very least, the
matters as described in 3.2.2.7.
3.2.2.7 The purpose of the EMC
would be:
To monitor and audit project
compliance to the specific conditions of this
record of decision, environmental legislation
and specific measures as stipulated in the environmental
impact report and the environmental management
plans
To make recommendations to the Director General:
DEAT on issues related to the monitoring and auditing
of the project.
The EMC shall be able to vary the frequency of
meetings should the need arise to review the prescribed
frequency of meetings. Any changes should be communicated
to the Department for acceptance.
The EMC shall be disbanded at a time to be determined
by the Department of Environmental Affairs (DEAT)
in consultation with the Department of Water Affairs
and Forestry (DWAF).
3.2.2.8 Upon completion of the construction phase
of the project, the roles, responsibilities and
constitution of the EMC shall be reconsidered
and the EMC shall be re-established with new TOR
for the operational phase of the development.
3.2.3 Authorities Co-ordinating
Committee
3.2.3.1 The Department of Water
Affairs and Forestry must, in addition, set up
an authorities co-ordinating committee;
3.2.3.2 Members of the authorities
co-ordinating committee shall be drawn from, but
shall not necessarily be limited to, the following
authorities:
Department of Environmental
Affairs and Tourism;
Mpumalanga Department of Agriculture and Land
Administration;
Limpopo Department of Finance and Economic Development;
Limpopo Office of the Department of Labour;
South African National Parks; and
Relevant affected municipalities.
3.2.3.3 The Committee shall meet at least four
times a year from the date of commencement with
pre-construction activities and the committee
shall be disbanded at the end of the construction
phase and following the rehabilitation of impacted
areas.
3.2.3.4 The responsibilities
of the authorities co-ordinating committee shall
include but not necessarily be limited to the
following:
To oversee that all commitments
in the record of decision (ROD) and the environmental
management plan (EMP) are met;
To provide guidance for the functioning of the
environmental monitoring committee (EMC);
To take into account all relevant information
and issues raised by stakeholders when making
project decisions; and to
Evaluate the reports and correspondence received
from the independent Chairperson of the EMC.
3.2.4 Independent Environmental Control Officer
(ECO)
3.2.4.1 The developer must appoint
a suitably qualified Environmental Control Officer
(ECO) who would on behalf of the EMC, on a daily
basis, monitor project compliance with the conditions
of the record of decision, environmental legislation
and recommendations of the EMP. The cost of the
ECO shall be borne by the applicant.
3.2.4.2 The ECO must be appointed
before the start of construction and pre-construction
related activities and the authorities must be
notified of such an appointment.
3.2.4.3 The ECO shall ensure
that monthly environmental performance audits
are undertaken on the project implementation.
3.2.4.4 The ECO shall submit
an environmental compliance report on a two-monthly
basis, in writing, to the Director General of
the Department of Environmental Affairs and Tourism
(DEAT), copied to the Mpumalanga Department of
Agriculture and Land Administration, Limpopo Department
of Economic Development, Environment and Tourism,
South African National Parks and relevant affected
Municipalities.
3.2.4.5 The ECO shall maintain
the following on site:
A daily site diary
A non-conformance register
A public complaints register
A register of audits
3.2.4.6 The ECO shall remain employed until all
rehabilitation measures, as required for implementation
due to construction damage, are completed and
the site is handed over to DWAF by the contractor
for operation.
3.2.4.7 The ECO shall report
to and be accountable to the EMC.
3.2.5 Environmental Management
Plan
3.2.5.1 Due to the nature and
extent of the proposed Olifants River Water Resources
Development Project (ORWRDP), and the proposed
mitigation measures, it is acknowledged that a
suite of environmental management plans will need
to be produced, as outlined below:
Pre-Construction EMPs
Construction EMPs
De Hoop Dam
R555 Realignment
Steelpoort River Weirs
National Bulk Water Distribution Infrastructure
De Hoop Dam or Steelpoort Abstraction Weir to
Olifantspoort Weir Pipeline and associated infrastructure
De Hoop Dam to Jane Furse Pipeline and associated
infrastructure
Flag Boshielo Dam to Mokopane Pipeline and associated
infrastructure
Post construction EMP
Operational EMP
3.2.5.2 Allied to Clause 3.2.4.1, the Department
of Water Affairs and Forestry must submit EMPs
to DEAT for acceptance before the commencement
of any of the activities related to this authorization
3.2.5.3 All EMPs contemplated
in Clauses 3.2.5.1 must include, but not necessarily
be limited to, the following aspects:
Mitigation measures recommended
in the Environmental Impact Report (dated October
2005).
Rehabilitation of areas to be disturbed during
the construction of the project.
Siting and management of construction camps outside
urban areas.
Access roads to individual construction areas.
Plant search and rescue before the commencement
of any construction activity,
Implementation of measures aimed at controlling
invasive plant species and weeds. The route alignment
and construction sites must be monitored for re-growth
of invasive vegetative material at least twice
a year for a period of up to two years after the
completion of this development.
Protection of the heritage sites likely to be
impacted by the construction of the dam and pipelines.
Waste avoidance and minimisation during construction.
Management of traffic during the construction
of the dam and the pipelines (where the pipelines
cross roads or other transportation networks).
The planning and implementation of a water conservation
and demand management strategy for the Olifants
Water Management Area in parallel with the construction
of infrastructure (i.e. approximately 10 years).
3.2.5.4 Once accepted by DEAT, the EMPs will be
regarded as dynamic documents. However, any changes
to the EMPs must be submitted to DEAT for acceptance
before changes are effected. Such a submission
to DEAT must be accompanied by recommendations
of the EMC.
3.2.5.5 Compliance with the
approved EMPs must form part of the project documentation
of all contractors working on the project, and
must be clearly indicated in all contractor’s
contracts.
3.2.6 Land acquisition
3.2.6.1 This development is
authorised on condition that the Department of
Water Affairs and Forestry acquires the necessary
land rights for that section of the project that
will be constructed according to the roll-out
plan.
3.2.7 Compliance with other
legislation
3.2.7.1 Archaeological remains
shall be dealt with as described in the relevant
EMPs.
3.2.7.2 The relocation of burial
sites must take place as advised in the report
from the archaeologist, after due public participation,
in terms of section 36 of the National Heritage
Resources Act, 1999, to accommodate the wishes
of the next of kin and descendants. Graves over
60 years old are protected by legislation and
permits from SAHRA are required for relocation
which may be granted only after a 60 day public
participation process. The SAHRA Limpopo office
has requested that a SAHRA official be present
during relocation of graves.
3.2.7.3 All sites indicated
as having scientific and research significance,
including several representative Late Iron Age
and Earlier Iron Age sites must be selected for
detailed archaeological Phase 2 mitigation. The
sites should be fully mapped and contextualised,
cultural material should be mapped, and recorded
and collected or excavated for future scientific
analysis. Samples must be taken for dating.
3.2.7.4 Appropriate measures
must be put in place (by prior arrangement with
the archaeologist) for the monitoring of earthworks
such as road building, quarrying, dam wall construction
and pipeline excavation.
3.2.7.5 Once the Phase 2 mitigation
has been completed by the archaeologist, permits
must be obtained by the developer for the destruction
of the remainder of the sites. This can be done
in a phased approach (preferably zone by zone)
to expedite the process.
3.2.7.6 No prospecting or mining
activities or extraction of any material shall
be conducted within the proposed project area,
or in relation to the proposed project without
necessary authorisations in terms of the Minerals
and Petroleum Resources Development Act, Act 28
of 2002.
3.2.7.7 Should prospecting or
mining activities take place within the proposed
project area in terms of the necessary authorisations
referred to in 3.2.7.6, or in relation to the
proposed project, all the provisions of the Mine
Health and Safety Act, 1996 must be complied with.
3.2.7.8 The Department of Water
Affairs and Forestry must verify with this office
prior to the commencement of the project that
there are no existing active old order prospecting
or mining activities and/or new prospecting and
mining applications accepted on any of the farms/
land within the proposed project area.
3.2.7.9 All provisions of the
Occupational Health and Safety Act, 85 of 1993
and any other applicable legislation must be adhered
to by the holder of this authorisation.
3.3 GENERAL CONDITIONS
3.3.1 This authorisation is
granted only in terms of section 22 of the Environment
Conservation Act, 1989 (Act 73 of 1989) and does
not exempt the holder thereof from compliance
with any other legislation.
3.3.2 This authorisation refers
only to the activity as specified and described
in the environmental impact report dated October
2005. Any other activity listed under section
21 of the Environment Conservation Act, 1989 (73
of 1989) which is not specified above, is not
covered by this authorisation, and must therefore
comply with the requirements of the Environment
Conservation Act, Government Notice R. 1182 and
R.1183 (as amended).
3.3.3 The applicant must, within
7 (seven) calendar days of receipt of this record
of decision inform all interested and affected
parties of the following:
That an authorisation has been
issued to the applicant to proceed with the construction
and operation of the activity. If requested, provide
copies of this ROD.
3.3.4 One week’s written notice must be given
to this Department before commencement of construction
activities. Such notice shall make clear reference
to the site location details and the reference
number of the project as indicated above.
3.3.5 One week’s written notice
must be given to this Department before commencement
of the operational phase activities. Such notice
shall make clear reference to the site location
details and the reference number of the project
as indicated above.
3.3.6 The applicant shall be
responsible for ensuring compliance with the conditions
contained in this ROD by any person acting on
its behalf, including but not limited to, an agent,
servant, or employee or any person rendering a
service to the applicant in respect of the activity,
including, but not limited to, contractors and
consultants.
3.3.7 The applicant must notify
the Department in writing, within 24 (twenty four)
hours if any condition of this authorisation cannot
be, or is not, adhered to. The notification must
be supplemented with reasons for non-compliance.
3.3.8 A copy of the authorisation
and ROD shall be available on site during construction
and all staff, contractors and sub-contractors
shall be familiar with or be made aware of the
contents of this authorisation and ROD.
3.3.9 Compliance/non-compliance
records must be kept and shall be made available
on request from the authorities within five days
of receipt of the request.
3.3.10 Any changes to, or deviations
from, the project description set out in this
letter must be approved, in writing, by the Department
before such changes or deviations may be effected.
In assessing whether to grant such approval or
not, the Department may request such information
as it deems necessary to evaluate the significance
and impacts of such changes or deviations.
3.3.11 This Department may review
the conditions contained in this letter from time
to time and may, by notice in writing to the applicant,
amend, add or remove a condition.
3.3.12 In the event that the
predicted impacts exceed the significance as predicted
by the independent consultant in the final environmental
impact report dated October 2005 and supporting
documentation, the authorisation may be totally
or partially withdrawn after proper procedures
have been followed.
3.3.13 In the event of any dispute
concerning the significance of a particular impact,
the opinion of the Department of Environmental
Affairs and Tourism (DEAT) in respect of its significance
will prevail.
3.3.14 The applicant must notify
the Department, in writing, at least 10 (ten)
days prior to the change of ownership, project
developer or the alienation of any similar rights
for the activity described in this letter. The
applicant must furnish a copy of this document
to the new owner, developer or person to whom
the rights accrue and inform the new owner, developer
or person to whom the rights accrue that the conditions
contained herein are binding on them.
3.3.15 Where any of the applicant’s
contact details change, including the name of
the responsible person/s, the physical or postal
address and/or telephonic details, the applicant
must notify the Department as soon as the new
details become known to the applicant, but not
later than 10 (ten) days thereafter.
3.3.16 National government,
provincial government, local authorities or committees
appointed in terms of the conditions of this application
or any other public authority shall not be held
responsible for any damages or losses suffered
by the applicant or its successor in title in
any instance where construction or operation subsequent
to construction is temporarily or permanently
stopped for reasons of non-compliance by the applicant
with the conditions of approval as set out in
this document or any other subsequent document
emanating from these conditions of approval.
3.3.17 If any condition imposed
in terms of this authorisation is not complied
with, the authorisation may be withdrawn after
30 days written notice to the applicant in terms
of section 22(4) of the Environment Conservation
Act, 1989 (Act 73 of 1989).
3.3.18 Failure to comply with
any of these conditions shall also be regarded
as an offence and may be dealt with in terms of
sections 29, 30 and 31 of the Environment Conservation
Act, 1989 (Act 73 of 1989), as well as any other
appropriate legal mechanisms.
3.3.19 The applicant shall be
responsible for all costs necessary to comply
with the above conditions unless otherwise specified.
A written commitment indicating acceptance of
this condition must be submitted to this department
prior to the dam construction.
3.3.20 Any complaint from the
public during construction must be attended to
as soon as possible. A complaints register must
be kept up to date and shall be produced upon
request.
3.3.21 Departmental officials
shall be given access to the construction areas
referred to under the project description above
for the purpose of assessing and/or monitoring
compliance with the conditions contained in this
document at all reasonable times.
3.3.22 All outdoor advertising
associated with this activity, whether on or off
the property concerned, must comply with the South
African Manual for Outdoor Advertising Control
(SAMOAC) available from this Department.
3.4 Duration of authorisation
If the activity authorised by
this letter does not commence within 5 (five)
years from the date of signature of this letter,
the authorisation will lapse and the applicant
will need to reapply in terms of the applicable
legislation or any amendments thereto.
4. CONSEQUENCES OF NON-COMPLIANCE
The applicant must comply with
the conditions set out in this letter. Failure
to comply with any of the above conditions may
result in, inter alia, the Department withdrawing
the authorisation, issuing directives to address
the non-compliance – including an order to cease
the activity – as well as instituting criminal
and/or civil proceedings to enforce compliance.
Please note that this revised
record of decision is issued as part of the Minister’s
decision on the appeals lodged in terms of Section
35(3) of the Act against the authorisation granted
by the Department of Environmental Affairs and
Tourism for this project on 21 November 2005.
5. APPLICANT:
Department of Water Affairs
and Forestry
Private Bag X 313
PRETORIA
0001
Contact person: Mr K Legge
Tel: (012) 336 8677
Fax: (012) 336 8561
6. CONSULTANT:
Acer Africa Environmental Management
Consultants
P O Box 503
MTUNZINI
3867
Contact person: Dr R-D Heinsohn
Tel: (035) 340 2715
Fax: (035) 340 2232
7. SITE VISIT
A site visit was undertaken
on 30 March 2005 by the following:
Mr Lesiba Ngoasheng - National
Department of Environmental Affairs& Tourism
Mr Wynand Fourie - National Department of Environmental
Affairs& Tourism
Mr Danie Smit - National Department of Environmental
Affairs and Tourism
Mr Paul Scherzer - Acer Africa
Dr R-D Heinsohn - Acer Africa
Mr Selby Hlatswayo - Mpumalanga Department of
Agriculture and Land Administration
Dr Garth Batchelor - Mpumalanga Department of
Agriculture and Land Administration
Mr Setenani Nkopane - Department of Minerals and
Energy
Ms Ntobenhle Thombeni - Land Claims Commission
Mr Khibi Mabuse - Department of Transport
Mr Thomas Maluleke - Department of Finance and
Economic Affairs
Ms Hellen Nonyane - Department of Finance and
Economic Affairs
Mr Zebedius Manku - Department of Agriculture
Mr Sekhwela Mokoena - Department of Health and
Welfare
Ms Seema Harmse - Department of Labour
Mr Papo Maloka - South African Association of
Local Government
Mr Martin Mahosi - Department of Local Government
and Housing - Limpopo
Mr Matodzi Silidi - Limpopo Road Agency
Dr Tinus Basson - BKS (Pty) Ltd
Mr Deon Esterhuizen - BKS (Pty) Ltd
Mr Jaap Kroon - Department of Water Affairs and
Forestry
Mr Ockie van den Berg - Department of Water Affairs
and Forestry
Mr Tendani Nditwani - Department of Water Affairs
and Forestry
Mr Theo van Rooyen - Capricorn District Municipality
Mr Parks Sebatjane - Waterberg District Municipality
Mr Gert Lombaart - Greater Groblersdal Municipality
Mr Michael Mabunda - Greater Tubatse Municipality
Mr Dan Malatjie - Department of Roads and Transport
– Mpumalanga
Mr Peet Meissenheimer - Department of Local Government
and Housing - Mpumalanga
MARTHINUS VAN SCHALKWYK, MP
MINISTER OF ENVIRONMENTAL AFFAIRS AND TOURISM
Riaan Aucamp
Annual Air Quality Governance
Lekgotla
Gearing up for the implementation of the Air Quality
Act
MONDAY, 16 JANUARY 2006 - SPEECH BY THE MINISTER
OF ENVIRONMENTAL AFFAIRS AND TOURISM, MARTHINUS
VAN SCHALKWYK, AT THE INAUGURAL AIR QUALITY GOVERNANCE
LEKGOTLA, EAST LONDON, 16 OCTOBER 2006
Today’s inaugural Annual Air
Quality Governance Lekgotla is a momentous occasion.
Today’s lekgotla shows that we are leading by
example – taking a progressive stance on an issue
of global importance and setting precedents for
governance within our own country. Today, we are
gearing up for the implementation of the Air Quality
Act – a piece of legislation that gives effect
to a clause in our Constitution, which makes us
world leaders on issues of social and environmental
justice. This clause says that all people have
the right to “an environment that is not harmful
to their health or well-being”. It goes further
to say that we have the right “to have the environment
protected, for the benefit of present and future
generations, through legislative and other measures
that prevent pollution and ecological degradation.”
Our Air Quality Act, which came
into effect in September last year, was heralded
as a “breath of fresh air” for the many South
Africans who have been breathing polluted air
for years. The Act provides for an implementation
plan that shows we are serious about delivery.
This lekgotla is a milestone that marks the first
national gathering of government air quality managers.
You will be working together as a team across
all three spheres of government, across the municipal
and provincial boundaries that are never recognised
by air pollution.
It is also fitting that on Wednesday,
you as government officials will engage with your
peers from industry and civil society to develop
the roadmap for air quality management for the
next five years, namely the National Air Quality
Management Framework. This framework will be published
on the 2nd anniversary of the Act coming into
effect in September next year.
It is also particularly important
that this lekgotla has been organised back to
back with the Annual Conference of the National
Association for Clean Air. It provides an opportunity
for all of you to interact with your peers from
industry, academia and civil society. You will
have the chance to debate issues of common interest
around air quality, and also to learn about new
approaches, new ideas and best practice in this
complex field of air quality management.
There are few people in this
room that will deny the challenges before us and
many of you may be asking yourselves, “Where do
we start?”
I believe we need to start by
establishing the extent of the problem and focussing
our attention on current and emerging threats
to air quality. To this end, in the very next
session, you will be presented with the results
of the South African Weather Service – Wits University
Aerial Survey. This exciting collaboration gives
us a snapshot of air quality in South Africa,
allowing us to identify current and future air
pollution hotspots and take appropriate action.
At a glance, it is clear that Secunda and the
general Witbank area are cause for concern. However,
the department will study this report and make
recommendations with a view to the identification
of the second National Priority Area in November.
Furthermore, it is also clear from the survey
that the levels of volatile organic compounds
in the general Highveld area needs further investigation
and confirmation at ground level.
Notwithstanding these initial
findings, this snapshot will be further enriched
by detailed information that will be contained
in our “State of the Air Report” which will be
published later this year. At this lekgotla the
first draft of this document will be circulated
for your comment and recommendations. This document
will ultimately identify exactly where we need
to focus our efforts. It will also be used as
the baseline against which we will measure the
effectiveness of our efforts in the coming years.
Furthermore, I have published
a new set of ambient air quality standards for
public comment and I have received numerous responses.
These comments will be used to inform the final
standards and, once published, they will provide
the objectives for all of our air quality interventions.
As such, we have a clear starting
point and a clear end point. However, it is the
“joining of the dots” that will be our work now
and into the future. Given the focus of this lekgotla,
it is clear that everyone has recognised our air
quality governance capacity constraints. The science
and practise of “cutting-edge” air quality management
has been on the decline for several years. As
a result, highly skilled and experienced air quality
managers are extremely rare. But skilled personnel
is only one component of our capacity challenge
and it will be necessary to address all the components
of effective capacity for effective service delivery.
In the short-term, the department’s
Atmospheric Pollution Prevention Act (APPA) Registration
Certificate Review Project, the so-called “Top
50 Polluter” project, has two specific objectives.
The first is to provide short to medium-term improvements
in air quality through reduced industrial emissions.
The second is to build capacity in provincial
and local spheres of government through “learning
by doing”. As such, I encourage all affected provinces
and municipalities to fully and actively participate
in this project over the next 18 months.
In this regard, I am expecting
the department’s recommendations on the initial
set of industries to be the subject of the review
within the next few weeks and, once I have approved
this list, the department will immediately get
into contact with all the affected provinces and
municipalities.
I have noticed a slogan on the
banners around these walls, proclaiming that “an
investment in air quality management is an investment
in public health”. It has been estimated that
the health impacts of pollution from fossil fuel
burning alone costs our fiscus R4 billion every
year. By way of comparison, the cost of implementing
the Air Quality Act is only R80 million. This
does not only make economic sense – it also gives
us the opportunity to fulfil our primary function
as government – improving the quality of life
for the citizens of our country.
Finally we need to combat the
idea that tighter air quality management will
restrict development. It is poor air quality that
does this. Good air quality management is good
for business and communities as it provides a
basis for all stakeholders to engage constructively
as good neighbours.
With these few words I wish
you a successful and productive lekgotla and I
urge you to fully exploit this precious opportunity
to strengthen the relationships you have so far
established through the various Air Quality Officers’
Forums and actively share your experiences and
common problems as equal partners in air quality
governance.
Riaan Aucamp