Panorama
 
 
 
 
 

STATEMENT ON THE CURRENT ROUND OF
CLIMATE NEGOTIATIONS IN POZNAN, POLAND


Environmental Panorama
International
December of 2008


FOR IMMEDIATE RELEASE: TUESDAY 2 DECEMBER 2008
MEDIA STATEMENT BY MARTHINUS VAN SCHALKWYK, SOUTH AFRICAN MINISTER OF ENVIRONMENTAL AFFAIRS AND TOURISM, TUESDAY 2 DECEMBER 2008
The climate negotiations in Poznan are expected to consolidate the political momentum and bring greater focus on the road to an agreed outcome by the end of 2009. The current negotiating round in Poznan is about gearing up to conclude negotiations on a binding, equitable, more effective and inclusive climate regime by the end of 2009 in Copenhagen.

We envisage six high-level outcomes in Poznan:

1. In Poznan we will be moving into full negotiating mode, thereby laying the basis for serious negotiations in 2009. To secure a deal at the end of 2009 in Copenhagen, we must outline a clear process and milestones for both negotiating tracks under the Bali Roadmap. We should bring new focus to the negotiations by revising the text that assembles all the creative proposals for a strengthened climate regime up to and beyond 2012. This will narrow down our negotiating agenda for next year to the key issues that must be resolved.

2. A Declaration by the COP President that captures the following elements in relation to a shared vision:

a) The over-arching shared vision should guide our efforts under both the Convention and Kyoto tracks.
b) A shared vision should balance climate and development and adaptation and mitigation - a recognition that solving the climate problem and making the transition to a low carbon economy will only be possible if any solution is undertaken with development priorities at its heart.
c) The guidance provided by the best available science and most ambitious IPCC scenario for climate stabilisation.
• For all developed countries this means a commitment to deep, absolute domestic emission cuts in the range of 80%-95% below 11000-levels by 2050, underpinned by credible mid-term targets in the 25%-40% range below 11000-levels by 2020.
• For developing countries, a substantial deviation below baseline in some regions by 2020 and all regions by 2050, on the basis of an equitable burden-sharing paradigm and binding delivery on the means of implementation (technology, financing and capacity) by developed countries

3. The Presidential Declaration should give a clear political signal that climate negotiations will intensify despite the global economic downturn. The current (temporary) financial crisis will not be allowed to diminish efforts to deal with the longer term climate crisis. In the face of a serious crisis, the world has now demonstrated that it is possible to raise significant amounts of money to meet a common global challenge.

4. Kyoto-ratifying developed countries should adopt an emission reduction range of at least 25%-40% below 11000 levels by 2020. This will give credibility and enable us to finalise ambitious mid-term targets for all developed countries within this range by the end of 2009, in time to avoid a gap between the 1st and 2nd commitment periods of the Kyoto Protocol and thus secure the carbon market. Without such an unambiguous commitment it will be very difficult to engage developing countries in a credible way to make their deviation below baseline "substantial".
• Japan, Russia, Australia and Canada have avoided putting their numbers on the table for too long. They now need to come forward with credible and ambitious mid-term targets within the 25% to 40% range for 2020. .
• From the US we expect comparability of commitments and compliance. We appreciate President-elect Obama's commitment to restore America's leadership in international global warming negotiations. In 2009, we will be looking to the US to come forward with ambitious commitments that will keep the world in the IPCC's most ambitious stabilisation scenario for 2020.

5. In respect of the legal form of the agreed outcome in Copenhagen, we are clear that it should be an "agreed outcome" that is legally binding and enforceable, in particular in respect of the means of implementation.

6. The final obstacles to make the Adaptation Fund Board operational in 2009, so that we can move to implementation, must be removed in Poznan.

Enquiries: Ronel Bester - +27 83 242 7763

Ministry of Environmental Affairs and Tourism
For immediate release

+ More

STATEMENT BY THE OFFICE OF MARTHINUS VAN SCHALKWYK, MINISTER OF ENVIRONMENTAL AFFAIRS AND TOURISM, ON 3 DECEMBER 2008

APPEALS DECISION AGAINST THE ENVIRONMENTAL AUTHORISATIONS OF THE PROPOSED CONSTRUCTION OF THE FOLLOWING TRANSMISSION LINES AND THEIR ASSOCIATED INFRASTRUCTURE FROM THE PROPOSED MEDUPI POWER STATION (NEAR LEPHALALE): ONE 400kV LINE TO THE MARANG SUBSTATION NEAR RUSTENBURG AND TWO 400kV LINES TO THE DINALEDI SUBSTATION NEAR BRITS

The Minister of Environmental Affairs and Tourism, Mr Marthinus van Schalkwyk, has considered the appeals lodged against the Department's Record of Decision of the proposed construction of the following transmission lines and their associated infrastructure from the proposed Medupi Power Station (near Lephalale): One 400kV line to the Marang Substation near Rustenburg and two 400 kV lines to the Dinaledi Substation near Brits.

After evaluating all the appeals and relevant information submitted to him, the Minister has come to a decision, a copy of which is attached hereto.

1. INTRODUCTION

In terms of section 22 of the Environment Conservation Act, 1989 (Act 73 of 1989) (ECA), read with the Environmental Impact Assessment Regulations published in Government Notice No. R. 1182 of 5 September 1997, the Director-General of the Department of Environmental Affairs and Tourism (DEAT) on 6 March 2008 and on 27 March 2008, acting under delegation in terms of section 33, authorised Eskom to proceed, respectively, with the construction of the following transmission lines and their associated infrastructure from the proposed Medupi Power Station near Lephalale:
* One 400kV transmission line to the Marang Substation
near Rustenburg;
* Two 400kV transmission lines to the Dinaledi Substation
near Brits.
After the authorisations had been issued, one appeal was lodged against each authorisation issued by the DEAT.

2. BACKGROUND

2.1 South Africa’s increasing economic growth rate necessitated an expansion of Eskom’s generation \ capacity, hence the construction of the new Medupi Power Station near Lephalale on the Waterberg Coal Fields was recently commenced with. On commissioning of the first generation unit of Medupi during 2010, it will be essential for the necessary transmission infrastructure, namely the Medupi-Marang and the Medupi-Dinaledi lines, to be in place to evacuate the available power. Construction of these lines will take approximately two years to complete. Once completed, the lines will provide supplementary energy to meet the growing need in the Brits and Rustenburg areas.

2.2 These proposed developments will comprise of the following:
2.2.1 Medupi-Marang transmission line
The Medupi-Marang transmission line consists of the construction of a 400kV transmission line of approximately 300km in length from the Medupi Substation near Lephalale (Limpopo Province) to the Marang Substation near Rustenburg (North West Province) as well as the construction of a 400kV transformer bay at the Medupi Substation and a 400kV feeder bay at the Marang Substation.

2.2.2 Medupi-Dinaledi transmission line
The Medupi-Dinaledi transmission line consists of the construction of two 400kV transmission lines of approximately 350km in length between the Medupi Substation, the Spitskop Substation near Northam (Limpopo Province) and the Dinaledi Substation near
Brits (North West Province) as well as the construction of two 400kV transformer bays at Medupi Substation, four 400kV feeder bays and two 400kV line turn innsI at Spitskop Substation, and two 400kV feeder bays at Dinaledi Substation.

3. APPEALS

3.1 One appeal was lodged against the environmental authorisations by the DEAT, against each of the proposed transmission line projects. The appeals originated only from the area between the Medupi Power Station and the Spitskop Substation near Northam. In this area the three proposed lines will share the same corridor with two existing 400kV transmission lines which originate from the Matimba Power Station near Lephalale.

3.2 Although the Medupi-Marang line and the Medupi-
Dinaledi lines are two separate projects and are the subjects of two individual authorisations by the DEAT, I decided to deal with the two appeals jointly for the following reasons:
3.2.1 For the major portion of their lengths - from Medupi to the existing Spitskop Substation near Northam - the three lines share the same corridor;
3.2.2 The appeals originated only from appellants located between Medupi and Spitskop, in other words, from that section of the route where the lines share the same corridor. No appeals were forthcoming from interested and affected parties situated in the areas south of Spitskop towards Marang and Dinaledi; and
3.2.3 With the exception of one minor item, the grounds of the appeals against both authorisations are identical.

3.3 The following emerged as the major grounds of appeal:
3.3.1 Inadequate public participation in the sense that the meetings arranged by Eskom’s consultants were “one way events” where very little opportunity was given for discussion of route alternatives;
3.3.2 Technological solutions proposed by the appellants were inadequately considered;
3.3.3 Insufficient information was provided to serve as a basis for the decision on the preferred route option;
3.3.4 The possible implementation of the “utility corridor” concept was ignored;
3.3.5 Unacceptable impacts on biodiversity in general and on certain bird species in particular;
3.3.6 The environmental impact assessments (EIAs) for these lines should have been integrated with the EIAs for the 765kV lines which are planned for construction during later phases of the provision of infrastructure for the Medupi Power Station; and
3.3.7 The independence of the environmental consultant is questioned in that the alternative proposed is a mere confirmation of the route preferred by Eskom.

4. DECISION

4.1 In reaching my decision on the appeals against the authorisation of these proposed transmission lines, I have taken the following into consideration:
4.1.1 The information contained in the project files (ref. 12/12/20/793 and 12/12/20/794, respectively);
4.1.2 The appeals submitted by the two appellants against the authorisation of the construction of the transmission lines between the proposed Medupi Power Station and the existing Marang and Dinaledi Substations;
4.1.3 The response of the applicant to the grounds of appeal and the appellants’ reply thereto;
4.1.4 The comments of the DEAT on the grounds of appeal, the applicant’s response and the appellants’ reply;
4.1.5 The urgent need for the establishment of these 400kV links to ensure the effective evacuation of power from the Medupi Power Station on commissioning of its first generation unit during 2010 to ensure a stable supplementary supply of electricity to meet the growing needs in the Brits and Rustenburg areas.

4.2 Having considered the above information, I have concluded that the Director-General of the DEAT adequately considered the major anticipated environmental impacts of the proposed development and that the decisions to authorise these proposed developments were correct. In addition, the mitigation measures proposed in the environmental impact report (EIR) and the conditions contained in the two Records of Decision (RODs) adequately mitigate the impact of the transmission lines to acceptable levels.
Therefore, in terms of section 35(4) of the ECA, I have decided to:

(a) Dismiss the appeals against the environmental authorisation granted by the Director-General of the DEAT for these two proposed transmission line developments; and
(b) Confirm the authorisations issued by the Director- General of the DEAT on 6 March 2008 for the construction of the Medupi-Marang 400kV transmission line and on 27 March 2008 for the construction of the Medupi-Dinaledi 400kV transmission lines.

4.3 The reasons for my decision, inter alia, are as follows:

4.3.1 The need for these developments has been adequately demonstrated.
4.3.2 The grounds of appeal are not, in my view, sufficient to warrant the setting aside of the original decision. In justification of my view I shall briefly discuss each of the major grounds of appeal below:
(a) The alleged deficiencies in the Public Participation Programme (PPP).
I am satisfied that the PPP met the requirements of the EIA Regulations and created sufficient opportunity to propose and discuss route options.

(b) Inadequate consideration of proposed technological solutions.
The appellants’ proposal that high voltage direct current (HVDC) be considered for these lines is impractical. I am advised that the implementation of such technology over such a relative short distance is not viable. I also accept the statement in the EIR that in the detailed planning of the lines attention will be given, in consultation with land owners, to the most appropriate tower structures to be used on specific terrain types.

(c) Insufficiency of the information provided for the route selection.
The statement in the appeal that “no factual and objective evidence were (sic) ever presented during the
PPP to confirm that the authorised route is in fact the most optimal route” is unfounded. I accept the comments submitted to me that all the reports on the specialist studies were available for perusal while the draft scoping report and EIR were made available for comment to all registered interested and affected parties (I&APs). The final route selection decision was based on this comprehensive base of information.

(d) The “utility corridor” concept could have been implemented more comprehensively. By routing the Medupi-Marang and Medupi-Dinaledi
lines between Medupi and Spitskop together with two existing 400kV lines a utility corridor will be created with its concomitant advantages of reduced impact on
biodiversity and facilitation of maintenance. However, the DEAT has drawn my attention to the fact that transmission lines are fire sensitive. Consequently, there is a limit to the number of lines that can be included in one such corridor as too many lines in one
corridor may cause a system collapse when veld fires occur. Therefore, I accept that in the implementation of the utility corridor concept, care should be taken to retain a balance between the environmental advantage and risk to the transmission system.

(e) Unacceptable impacts on biodiversity in general and on certain bird species in particular.
It is acknowledged in the EIR that the impact of the lines on biodiversity will be significant, regardless of whether an eastern or western alignment is followed. However, the sensitivity analysis done during the scoping phase of the EIA indicated that environmental sensitivity for this development gradually decreases towards the west.
Additionally, the fact that the lines will be placed in an existing corridor with existing 400kV lines will soften the impact on vegetation and no new access or service roads need to be constructed. Furthermore, the specialist ornithological studies showed that the impact on avifauna will be higher should the lines be constructed along an eastern corridor. Therefore, although there will be an impact on the flora and fauna in the area, I am satisfied that care has been taken to ensure that a route will be followed which will cause the least disruption to the ecosystems that will be traversed.

(f) The EIAs for the Medupi-Marang and Medupi-Dinaledi lines should have been integrated with the EIA for the 765kV transmission lines.
I am aware of the studies undertaken by Eskom to ensure the effective integration of the proposed Medupi Power Station into the national transmission network and concur that planning in this regard must be integrated as far as possible. In view thereof, I accept that the awarding of priority to the planning and the assessment of the environmental impact of the Medupi- Marang and Medupi-Dinaledi lines is determined by the phased commissioning of the generation units of the Medupi Power Station and the electricity needs, in the short term, of the Brits and Rustenburg areas. Hence, the establishment of the Medupi-Marang and the Medupi- Dinaledi lines is of a higher priority than the 765kV transmission lines. The planning of the former lines can therefore not be delayed to be integrated with the planning of the 765kV lines, which will be needed at a later stage to evacuate power to the Epsilon Substation near Potchefstroom.

(g) The independence of Eskom’s environmental assessment practitioner (EAP) is questioned.
I am advised and accept that the independence of PBA International (SA), Eskom’s EAP, is above suspicion.
The information contained in the EIR was independently evaluated and corroborated by the DEAT and the recommendations made by the EAP were considered to be well-balanced and objective. Therefore, I am satisfied that a well-informed and sound decision was taken on this development proposal.

(h) Lines along the authorised route will be longer and will cause more pollution due to greater power losses I have noted that due to its increased length (15km), the power losses from the lines along the authorised route will cause an increase of approximately 0,003% in pollution from the power station and that for the sector such an increase is regarded as insignificant.

(i) Decisions on the establishment of transmission infrastructure associated with the Medupi Power Station are being taken incrementally The fact that the development of the Medupi-Marang and Medupi–Dinaledi transmission lines precedes the planning and the establishment of other transmission lines in the area and, consequently, may influence decisions on the routing of those lines, may be perceived as incremental decision making. However, the current approach is dictated by the enormity of the Medupi Power Station which, due to its extended construction period, will need transmission facilities at different intervals.

(j) Undue consideration was given to avoiding undermined areas I accept the information provided to me by the DEAT regarding the consequences of the construction of transmission lines over undermined areas. Not only does it place a high degree of risk on such lines as well as on the integrity of transmission systems, it also impacts on the operation of a mine due to restrictions on blasting, for instanceI.

4.4 The reasons set out above are not exhaustive and should not be construed as such and I reserve the right to provide comprehensive reasons for the decision should this become necessary.
MARTHINUS VAN SCHALKWYK, MP
MINISTER OF ENVIRONMENTAL AFFAIRS AND TOURISM

 
 

Source: South African Environmental
Press consultantship
All rights reserved

 
 
 
 

 

Universo Ambiental  
 
 
 
 
     
SEJA UM PATROCINADOR
CORPORATIVO
A Agência Ambiental Pick-upau busca parcerias corporativas para ampliar sua rede de atuação e intensificar suas propostas de desenvolvimento sustentável e atividades que promovam a conservação e a preservação dos recursos naturais do planeta.

 
 
 
 
Doe Agora
Destaques
Biblioteca
     
Doar para a Agência Ambiental Pick-upau é uma forma de somar esforços para viabilizar esses projetos de conservação da natureza. A Agência Ambiental Pick-upau é uma organização sem fins lucrativos, que depende de contribuições de pessoas físicas e jurídicas.
Conheça um pouco mais sobre a história da Agência Ambiental Pick-upau por meio da cronologia de matérias e artigos.
O Projeto Outono tem como objetivo promover a educação, a manutenção e a preservação ambiental através da leitura e do conhecimento. Conheça a Biblioteca da Agência Ambiental Pick-upau e saiba como doar.
             
       
 
 
 
 
     
TORNE-SE UM VOLUNTÁRIO
DOE SEU TEMPO
Para doar algumas horas em prol da preservação da natureza, você não precisa, necessariamente, ser um especialista, basta ser solidário e desejar colaborar com a Agência Ambiental Pick-upau e suas atividades.

 
 
 
 
Compromissos
Fale Conosco
Pesquise
     
Conheça o Programa de Compliance e a Governança Institucional da Agência Ambiental Pick-upau sobre políticas de combate à corrupção, igualdade de gênero e racial, direito das mulheres e combate ao assédio no trabalho.
Entre em contato com a Agência Ambiental Pick-upau. Tire suas dúvidas e saiba como você pode apoiar nosso trabalho.
O Portal Pick-upau disponibiliza um banco de informações ambientais com mais de 35 mil páginas de conteúdo online gratuito.
             
       
 
 
 
 
 
Ajude a Organização na conservação ambiental.